Project Summary

TNB, through its subsidiary TNB Power Generation, has received approval to implement the Hydro Life Extension Program (HLEP) for Sungai Perak’s hydro plants (650.75 MW).The program will refurbish six power stations (18 units) starting in 2024, with the first unit set for operation in 2025 under a new 40-year Power Purchase Agreement.

 

This will boost TNB’s total hydro capacity to 2,661 MW. HLEP aligns with TNB’s Net Zero 2050 goal and Malaysia’s Low Carbon Aspiration 2040. The project is expected to enhance earnings without affecting TNB’s net assets before commissioning.

H2P’s Scope in TEMEGOR, BERSIA & KENERING HYDROPOWER PLANT

TEMENGOR, BERSIA, KENERING

  • Worker’s Accommodation (CLQ)
  • Expatriate Camp
  • Site Office
  • Storage and Scrapyard
  • Operations and Maintenance

APPOINTED SUB-CONTRACTOR & CONSULTANT:

KAMAL ENGINEERING SDN BHD

Kamal Engineering Sdn Bhd (KESB) was selected as H2P’s contractor for the TBK project with the following scope of work,

  • Design Drawings for all Site Facilities & Accomodation
  • Supply & Construction for all Site Facilities & Accomodation
  • Carrying Survey Work & Utility Mapping
  • Conducting Soil Investigation
  • Site Clearing & Landscaping

BJP CONSULT SDN BHD

BJP Consult Sdn Bhd was selected as H2P’s lead consultant for the TBK project with the following scope of work,

  • Contract Works Consultancy Services
  • Project Operational Support Services

TBK PROJECT SITES:

TEMENGOR

  • Renovation of existing TNB site office
  • Construction of temporary site office for HeiTech-Voith
  • Construction of temporary storage area

BERSIA

  • Construction of new site office for TNB on the roof of existing HQ
  • Construction of temporary site office for HeiTech-Voith
  • Construction of temporary storage area

KENERING

  • Construction of temporary site office for HeiTech-Voith
  • Construction of temporary storage area
  • Construction of worker’s accommodation outside TNB Hydroelectric Station area

BANDARIANG

  • Construction of worker’s accommodation
  • Construction of expatriate housing